crconcrete

#StrengthInConcrete

WSDOT Barker Rd Interchange

PROJECT DETAILS

 

Contract Type:  Subcontractor

Client: WSDOT

Partners/GC: Inland Asphalt

Divisions: Site Concrete, Structural Concrete

 

SUMMARY

The I-90 Barker Rd Interchange Improvement was an extremely challenging project, that only had 45 working days to complete. CR was tasked with completing two RABs with colored and stamped concrete, a structural wall, new sidewalks and over mile curbing. The CR crews placed over 1250 CY of concrete in only 15 working days.

More Projects